Most buyers receive a box of samples and a short email: "T1 samples are ready, please confirm." The parts look good, so they approve. Three months later, mass production shows flash on one cavity, a dimension drifting out of tolerance, or a cycle time 30% longer than quoted.
The problem is rarely the mold alone. It is that each trial stage was approved without knowing what it was supposed to prove. This article explains the purpose of each stage for liquid silicone rubber (LSR) tooling and what evidence buyers should ask for.
LSR behaves differently from thermoplastics. It has very low viscosity, so it flashes into gaps as small as a few microns. It cures by heat inside a hot mold rather than solidifying as it cools. And it shrinks after demolding and again during post-cure.
That means a part can look perfect at the press and still change size after post-cure. It also means a mold that fills well with a hand-adjusted process may not repeat once the process is locked. Trials must test repeatability, not just appearance.
|
Stage |
Main purpose |
Buyer should receive |
Approve if |
|---|---|---|---|
|
T0 |
Mold runs; filling and venting checked |
Short-shot study, photos of first full parts |
Not for approval — internal check |
|
T1 |
Part geometry and function |
Full dimensional report per cavity, process sheet, samples |
Dimensions and function meet drawing, or deviations are listed with a fix plan |
|
T2 (and later) |
Corrections verified |
Re-measured dimensions on corrected features, change log |
All T1 issues closed |
|
Pre-production run |
Stability at production settings |
Capability data on key dimensions, cycle time, scrap rate |
Process is stable and repeatable |
T0 is an internal trial. The molder checks that the mold opens, closes and fills, that vents work, and that the cold runner and needle valves behave. A short-shot study, filling the cavity in steps, shows where material flows last and where air may be trapped.
Buyers rarely need T0 samples. But it is reasonable to ask for short-shot photos. They reveal whether venting and gate position were designed correctly.
T1 is where geometry is judged. For a multi-cavity LSR mold, insist on measurement of every cavity, not one "best" part. Cavity-to-cavity differences are common and only show up when each is measured.
Ask that T1 parts be measured after post-cure, using the same post-cure profile planned for production. Measuring before post-cure is one of the most common reasons approved samples do not match mass production.
A T1 report should include:
T2 exists to confirm corrections. The report should focus on features that changed and show they now meet the drawing. Ask for a change log listing what steel was cut or added, so the tooling history stays traceable.
If T2 introduces new problems, do not skip ahead. Each extra trial is far cheaper than repairing a mold after mass production has started.
A pre-production run, often a few hundred to a few thousand shots, tests whether the mold and process stay stable for hours, not minutes. This is where you confirm:
For medical, baby care and automotive parts, this run is also where capability data on critical dimensions is collected.
Approve a stage only when you know what it was meant to prove and you have seen evidence that it did. Appearance is not evidence. Measurements, process sheets and run data are.
At TYM, every LSR mold trial comes with a cavity-by-cavity dimensional report and the process sheet used. To plan validation for your next silicone part, contact our engineering team at sales@tymmold.com.